In a RACI chart, which category involves people who should be informed about the project's outcomes?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Enhance your project management skills with our Google Project Management Professional Certificate quiz. Test your knowledge with flashcards and multiple choice questions. Prepare effectively for your certification exam and boost your career opportunities.

In a RACI chart, the category that involves people who should be informed about the project's outcomes is "Informed." This designation pertains to individuals or groups who do not directly participate in the project but need to be kept up to date on progress, changes, and results. Their involvement is crucial for transparent communication and ensuring that all stakeholders are aware of the project's status, enabling them to align their efforts or make informed decisions based on the project's outcomes.

The other categories serve different purposes: those designated as "Responsible" are the individuals completing the tasks, while "Accountable" refers to the person who is ultimately answerable for the project's success. "Consulted" includes those whose opinions are sought, often involving two-way communication for obtaining feedback or expertise, but they are not primarily focused on being informed about outcomes.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy